.. _open_tendering: Tendering ========= Open procedure has `active.tendering` status and can be represented with the following diagram: .. image:: _static/active-tendering.png Constraints ----------- - `tenderPeriod` cannot be shorter than 7 days. - `enquiryPeriod` always ends 3 days before tenderPeriod ends. - If tender conditions are modified with less than 4 days left to `tenderPeriod.endDate`, this period should be extended so that from the moment of the change in the tender documentation until `tenderPeriod.endDate` has remained at least 4 days. Claims and Complaits ~~~~~~~~~~~~~~~~~~~~ - Claims can be submitted only if there are more than 3 days left in tenderPeriod. - Complaints can be submitted only if there are 3 or more days left in tenderPeriod.